Lakeline-Parmer Ln (CP342) New Feeder

The Lakeline-Parmer Lane Project was a Capital Improvement Project initiated to relieve loading constraints along the Lakeline Drive and Parmer Lane corridors.
The project consisted of the installation of a new overhead and underground 25kV circuit from the Avery Ranch Substation and rebuilding of the existing overhead. Routing and spacing constraints required 420 feet of underground, 3-phase using 1000 mcm aluminum conductor to parallel an existing double circuit overhead line and 138kV transmission line to a 96”x96” precast vault on Staked Plains Drive. From the vault, the underground portion of the line continued to Lakeline Drive, where it was converted to an overhead 795 AAC (Arbutus) to Parmer Lane was identified.

During the ROW acquisition efforts, the decision was made to relocate the section of line within the Lakeline Drive ROW, due to the critical need for project completion and the time requirements of dealing with a single contentious land owner. As this portion was within the City of Austin ETJ, extensive coordination was required with the City of Austin, Austin Water, and other dry utilities. The route also required extensive coordination and permitting to cross the existing Capital Metro rail system with a new overhead single circuit line.

From the Lakeline Drive intersection, 3,800 feet of the existing single circuit 336 AAC overhead line along Parmer Lane was reconfigured and re-built to accommodate the new 795 AAC configuration to FM 1431 and was extended an additional 3,600 feet to support the higher load demands. After crossing Brushy Creek, the circuit was again transitioned to underground 1000 mcm aluminum conductor, ultimately terminating at the FM 1431 and Parmer Lane intersection and tied into and existing double circuit feeder. Airbreak switches and reclosers were installed in two locations, at Parmer Lane and Brushy Creek Road, and just south of the Brushy Creek crossing to provide load switching and coordinated protection along the feeder.

This is the start of a Successful Relationship

Testimonials

Highest Level of Professional Engineering

M&S has been Southstar’s Civil Engineer for over 7 years and our success is a direct result of their stellar work. From their leadership down to the company’s focus and ideals M&S represents the highest level of professional engineering. They are focused on their client and understand our goals and challenges. Southstar would not be the company nor our projects be the success they are unless we had M&S by our side.

Thad Rutherford
Southstar Communities

M&S Engineering
5
2020-06-12T13:19:22-05:00

Thad Rutherford
Southstar Communities

M&S has been Southstar’s Civil Engineer for over 7 years and our success is a direct result of their stellar work. From their leadership down to the company’s focus and ideals M&S represents the highest level of professional engineering. They are focused on their client and understand our goals and challenges. Southstar would not be the company nor our projects be the success they are unless we had M&S by our side.

Focused on Developing Relationships

This partnership we have forged will launch our District well into the future. With a supportive Board we have focused on developing relationships that bond us with our consultants as partners rather than tools that we use. We feel that we have a very symbiotic relationship with our team at M&S.

Mike Taylor
Crystal Clear Special Utility District - General Manager

M&S Engineering
5
2020-06-12T13:22:11-05:00

Mike Taylor
Crystal Clear Special Utility District - General Manager

This partnership we have forged will launch our District well into the future. With a supportive Board we have focused on developing relationships that bond us with our consultants as partners rather than tools that we use. We feel that we have a very symbiotic relationship with our team at M&S.

Project Coordination Heroes

M&S is one of the most responsive firms that I have worked with, which improves our project coordination process.

Tim S. Gescheidle,
AIA

M&S Engineering
5
2020-09-17T14:01:58-05:00

Tim S. Gescheidle,
AIA

M&S is one of the most responsive firms that I have worked with, which improves our project coordination process.

True Partners

The staff at M&S has been fundamental in building the CIP for Crystal Clear SUD and in guiding the board of directors in all aspects of the overall concepts utilized.  They have been able to explain things in manageable segments that have assured understanding at all director experience levels.  We greatly appreciate their professionalism and true partnership with the Crystal Clear organization.

Donald Bosworth ,
Crystal Clear Special Utility District - Board President

M&S Engineering
5
2020-09-17T14:04:16-05:00

Donald Bosworth ,
Crystal Clear Special Utility District - Board President

The staff at M&S has been fundamental in building the CIP for Crystal Clear SUD and in guiding the board of directors in all aspects of the overall concepts utilized.  They have been able to explain things in manageable segments that have assured understanding at all director experience levels.  We greatly appreciate their professionalism and true partnership with the Crystal Clear organization.
5
4
M&S Engineering