Client Spotlight: Bergheim Substation in Bergheim, TX
Pedernales Electric Cooperative is experiencing load growth in their service territory west of the Bulverde area, near the Hwy. 46/Blanco Rd. intersection. With this comes the need for a substation expansion to help serve those PEC members. M&S Engineering designed the addition of a single breaker bay to the 138 kV bus at Bergheim Substation near Bergheim, Texas. The new bay includes a 138 kV circuit switcher and a 46 MVA, 138 kV to 25 kV power transformer. The distribution side of the transformer will include a 25kV total breaker, tie breaker, and four feeder breakers.
Cory Kadlacek, P.E.
Spring Branch, TX
(830) 228-5446
(830) 228-5446